J85K HF Tower project
Work in progress
Tower Base section
Main section, onto its pivot point
J8WUF keeps a close eye on the lift
Tower Base section
1/8
J85K Tower erection
-
Base Section planted onto bolts
-
Stage 1 section onto its pivot point
-
'Gin Pole' Tower with raising mechanism
-
Stage 2 section (1/2) as 'counter-balance'
-
Ricky_J88CG raising Main tower
-
Stage 2 section -- Rotor cage
-
J8WUF keeps a close eye on the proceedings
Supervising Site Engineer J8WUF
Tower base excavaction - 6 Cu Yd.
Final rebar cage
Supervising Site Engineer J8WUF
1/4
Tower Base Build
Rex_J8WUF -- Site Works Engineer, examines the base excavation prior to clean-up and concrete pour.
Conditions only allowed casting on Saturday to about 2/3 level and we completed the base block on the following Monday.